Proposal/Job Go Back
Proposal/Job Information
United Farmers Cooperative - Brownton, MN 55312
73x32 LNR UTL Proposal 2022
HTS-4134-0122
Liner - New
0.00
n/a
1/07/2022
73679.00
Proposal
n/a
0.00
4/15/2022
n/a
Job Details/Notes
Chris Schultze
Material: $51,990
Geotextile: $4,379
J Bolts: $3,060
Total: $59,429
Installation/Travel: $14,250
Travel Days: 2.25
Installation Days: 2.5
If two liners are signed for, the total would be $147,358
Option:
60 mil bottom with 40 mil shell add: $8,071
Material: $51,990
Geotextile: $4,379
J Bolts: $3,060
Total: $59,429
Installation/Travel: $14,250
Travel Days: 2.25
Installation Days: 2.5
If two liners are signed for, the total would be $147,358
Option:
60 mil bottom with 40 mil shell add: $8,071
Address Information
Jim Carlson
Jim Carlson
Brownton
MN
Tank Information
0
n/a
n/a
Inspection Information
n/a
Liner Installation Stage
n/a
Documents